New York lost 6.5 gigawatts of offshore wind contracts, and 2 of its 5 auctions ended with no awards

Developers cancelled offshore wind projects and blamed inflation, interest rates and supply chains. Orsted alone wrote off 4 billion dollars on 2 New Jersey projects it will never build.

422megawatts of offshore wind actually running in 2022, when developers were planning more than 6,000
4 billion5dollars written off by Orsted on 2 New Jersey projects
01awards from 2 of the 5 New York offshore wind auctions

What was promised

In June 2022 the federal energy statistics agency counted more than 6 gigawatts of offshore wind that developers planned to build along the east coast by 2029. What was actually spinning at that moment was 42 megawatts, a 30 megawatt wind farm off Rhode Island and a 12 megawatt pilot off Virginia. The plans were roughly 150 times the size of the reality.

How a contract dies

A contract dies when building costs rise above the price the developer agreed to. A state runs an auction, and developers bid the price they will accept per unit of electricity for the next 20 years or so. The winner signs, then spends 5 or 6 years surveying, permitting and ordering steel. The price is fixed on day one. The costs are not.

New York offshore wind contracts that did not survive
Terminated after signing2,490Selected, never finalised4,032010002000300040005000megawatts

Both bars are sums of the project sizes listed by the state agency. Together they come to 6,522 megawatts.

Source 1.

Show the numbers
Terminated after signing2,490
Selected, never finalised4,032

New York ran 5 of these auctions. The 2020 round awarded 2 contracts, Empire Wind 2 and Beacon Wind, worth 2,490 megawatts between them, and both were later terminated. The 2022 round picked 3 more projects worth 4,032 megawatts, then closed in April 2024 with no final awards at all. The fifth round closed in February 2026 the same way. That is 6,522 megawatts of contracts that went nowhere, from the state agency record.

Which projects were cancelled

Offshore wind projects cancelled between July 2023 and January 2024
Empire Wind 21,260SouthCoast Wind1,200Commonwealth Wind1,200Ocean Wind 21,148Ocean Wind 11,100Park City Wind80404008001200megawatts

Sizes for the 2 Ocean Wind projects come from source 5. Revolution Wind 2 was also cancelled but no size was published, so it has no bar.

Source 4.

Show the numbers
Empire Wind 21,260
SouthCoast Wind1,200
Commonwealth Wind1,200
Ocean Wind 21,148
Ocean Wind 11,100
Park City Wind804

Between July 2023 and January 2024 developers walked away from Commonwealth Wind and Park City Wind in Massachusetts, SouthCoast Wind, Revolution Wind 2, Empire Wind 2, and Ocean Wind 1 and 2 in New Jersey. Every developer named the same 3 things. Inflation, interest rates, and a supply chain that could not deliver vessels and steel on the old schedule. Avangrid said plainly that Park City Wind had become unfinanceable.

We are extremely disappointed to announce that we are ceasing the development of Ocean Wind 1 and 2.

Mads Nipper, chief executive of Orsted, in October 2023. Source 5.

Who eats the cost

Orsted took 4 billion dollars of write downs when it stopped Ocean Wind 1 and 2, and 2.8 billion of that was Ocean Wind 1 by itself. That part lands on shareholders. The rest lands on the states. New Jersey lost 2 projects it had built a policy around, and New York went through 2 auction rounds that produced nothing while the clock on its own targets kept running.

By July 2024 the federal energy statistics agency had cut 2,400 megawatts out of its own outlook, leaving 4,800 megawatts still in development. The projects that survived are real and several are now turning. The gap between 6 gigawatts of plans and what got built is the cost of writing a fixed price into a contract 6 years before anybody pours concrete.

Sources

  1. Offshore Wind Solicitations. New York State Energy Research and Development Authority. Accessed 2026-08-27.
  2. Developers plan to add 6 gigawatts of U.S. offshore wind capacity through 2029. United States Energy Information Administration. Published 2022-06-30. Accessed 2026-08-27.
  3. Cancellations reduce expected U.S. capacity of offshore wind facilities. United States Energy Information Administration. Published 2024-07-09. Accessed 2026-08-27.
  4. Gone with the wind, tracking sunken U.S. offshore wind projects. Sean Wolfe, Renewable Energy World. Published 2024-01-08. Accessed 2026-08-27.
  5. Orsted cancels two offshore wind projects along New Jersey coast. Diana DiGangi, Utility Dive. Published 2023-11-01. Accessed 2026-08-27.

Was this article helpful

Back to the home page