Green steel plant in Sweden clears 2 big hurdles but still is not making steel

Stegra closed a 1.4 billion euro financing round in June 2026, and the hydrogen tower at its Boden plant in northern Sweden reached its full height the same month, but the company still needs 18 to 24 months after construction finishes before the plant actually makes steel.

145 meters2the height the direct reduction tower at the Boden plant in Sweden reached in June 2026
1.4 billion euros3the financing round Stegra closed in June 2026 to finish building and commissioning the plant
18 to 24 months4how long independent reporting says it takes after construction finishes before the plant actually produces steel

Green steel plant in Sweden clears 2 big hurdles but still is not making steel

A green steel plant in Sweden cleared 2 major hurdles in 2026, but it still has not made any steel. Stegra is building the plant in Boden, a town in northern Sweden, to make steel using hydrogen instead of coal. Hydrogen made by splitting water with clean electricity, a process called electrolysis, replaces the coal that traditional steel mills burn to strip oxygen from iron ore, a step called direct reduction. Stegra says the swap cuts carbon dioxide emissions by up to 95% compared with the traditional coal based method, a figure that is the company own claim, not independently checked by any source this article used.

In June 2026 the plant own direct reduction tower, the 145 meter structure where hydrogen actually replaces coal, reached its full height. That same month Stegra closed a 1.4 billion euro financing round to finish building and commissioning the rest of the plant. Neither milestone means the plant is making steel. Independent reporting from April 2026 says finishing construction still leaves another 18 to 24 months of commissioning before steel production actually starts, and Stegra own construction partner still described the site as being built, not running, as recently as September 2026.

A funding crisis came before the financing win

The 1.4 billion euro close followed a real scare. In December 2025 the Swedish Energy Agency awarded Stegra only 41 million euros through its Industriklivet grant programme, a quarter of the 168 million euros the company had requested. Stegra still needed to raise about 1 billion euros more by spring 2026 just to keep building. Leif Johansson, an adviser to the investor group behind the plant, said the half finished mill running at only a fraction of its planned pace made him sad to see as an industrialist, a sign of how close the project came to stalling. Hakan Buskhe, Head of Special Investments at Wallenberg Investments, one of the investors behind the June close, called the round a step for the country own competitiveness.

This large-scale green project represents an important step in Sweden's competitiveness and the EU's security of supply.

Hakan Buskhe, Head of Special Investments at Wallenberg Investments. Source 3.
The funding gap Stegra faced before the June 2026 closeRequested but not receivedActual money
02505007501000168Requested,grant41Awarded,grant1000Still needed,by spring 2026millions of euros

The still needed figure is Stegra own estimate of what it had left to raise as of December 2025, reported by GCN, the amount the June 2026 financing round in the next chart later closed.

Source 5.

Show the numbers
Requested, grant168
Awarded, grant41
Still needed, by spring 20261000

The financing closed on June 24, 2026. Counting that new round, Stegra has now raised 6.5 billion euros in loans and equity, on top of the earlier 41 million euro government grant.

The money that financed finishing the Boden plant
020004000600041Energy Agency,grant1400June 2026,financing round6500Total raised,in loans and equitymillions of euros

The 3 bars are 3 separate amounts, not parts that add up to a total. The 41 million euro grant is sourced to the Swedish Energy Agency award, source 5, the same figure shown in the funding gap chart above. The 6,500 million euro total is sourced to Stegra own site and Canary Media, sources 1 and 4, and was raised before this round.

Source 3.

Show the numbers
Energy Agency, grant41
June 2026, financing round1400
Total raised, in loans and equity6500

The plant is still under construction, not running

Stegra own technical description of the Boden plant lists a 700 megawatt hydrogen electrolyzer, the machine that splits water into hydrogen using electricity, built across a 270 hectare site, figures found by reading the company own page directly. A second tower, the 110 meter melt shop where the steel itself gets its final treatment, reached its full height in March 2025. Canary Media reported the plant was 60% complete as of fall 2025, and that Stegra own original goal of finishing construction by late 2026 is now under review.

Caroline Ashley, Executive Director of the industry group SteelWatch, called the financing close a sign of real progress.

Stegra securing the future of its Boden green steel plant is a welcome development that signals the change towards truly clean steelmaking at scale is happening.

Caroline Ashley, Executive Director of SteelWatch. Source 4.

The progress she describes still needs those 18 to 24 months of commissioning in northern Sweden before the plant actually makes steel.

Sources

  1. Stegra, company homepage. Stegra. Accessed 2026-09-16.
  2. Stegra, the Boden plant page. Stegra. Accessed 2026-09-16.
  3. Stegra announces closing of 1.4 billion euro financing round. Stegra, company press release. Published 2026-06-24. Accessed 2026-09-16.
  4. Stegra lands funding to complete world's first major green-steel mill. Maria Gallucci, Canary Media. Published 2026-04-14. Accessed 2026-09-16.
  5. Stegra Wins 41 Million Euro Grant To Build Facility. Edwin O., GCN. Published 2025-12-09. Accessed 2026-09-16.

Was this article helpful

Back to the home page