Texas approves a huge new 765 kilovolt power line for West Texas, clearing more than 400 miles to feed the Permian Basin oil fields

On August 28, 2026, the Public Utility Commission of Texas approved more than 400 miles of new 765 kilovolt transmission line running from Somervell County westward toward the Permian Basin, the first lines built at that voltage anywhere in Texas, meant to shorten a wait of more than 2 years for oil and gas operators trying to connect new equipment to the power grid.

more than 400 miles1of new 765 kilovolt transmission line Texas regulators approved for the Permian Basin, the first lines built at that voltage anywhere in Texas
100 billion dollars2estimated lifetime cost of the wider 765 kilovolt program once financing, equity returns, maintenance and taxes are counted, according to a state senator
more than 2 years1the wait oil and gas operators in the Permian Basin already face to connect new equipment to the power grid

Why Texas is building a huge new power line in West Texas

Texas is building a huge new power line in West Texas to feed the Permian Basin oil fields, where operators already wait more than 2 years to connect new equipment to the power grid. On Friday, August 28, 2026, the Public Utility Commission of Texas unanimously approved 2 Oncor transmission projects, docket numbers 59315 and 59029, clearing more than 400 miles of new 765 kilovolt transmission line running from Somervell County westward toward the Permian Basin, the first lines built at that voltage anywhere in Texas. A kilovolt measures electrical pressure, and a 765 kilovolt line carries far more power over long distances than the 345 kilovolt and 138 kilovolt lines already crossing Texas, so fewer new lines move the same power. Together the 2 routes make up import path 1, 1 of 3 planned import paths meant to relieve the region. Oncor expects the first segment complete by 2028 and the second by 2029, though legal challenges could push both back.

A law that cut the deciding time in half

The approval moves this fast because of Texas House Bill 5066, passed by the Texas Legislature in 2023 with only 3 of 181 lawmakers voting against it. The bill ordered the Electric Reliability Council of Texas, the operator of the state grid, to write a Permian Basin specific reliability plan by January 30, 2024, approved by the commission in April 2025. It also cut how long the commission can take to decide a transmission application, from 1 year down to 180 days after filing, a cut of 185 days, a bit more than half the old wait, a figure this site calculated from the before and after numbers the bill itself states rather than one the bill gives directly. That faster clock is why 2 lines opposed by hundreds of landowners still cleared the commission on schedule.

How fast Texas regulators must decide a new transmission line
0100200300400365Standard timeline,before the 2023law180Timeline underHouse Bill5066days

The drop of 185 fewer days is a subtraction this site made from the 2 numbers source 5 states directly, not a figure source 5 gives as a single number.

Source 5.

Show the numbers
Standard timeline, before the 2023 law365
Timeline under House Bill 5066180

Why regulators chose fewer, bigger lines

A coalition backing the buildout, Texans for Responsible Infrastructure Investment, says the Permian Basin has averaged 11% annual peak power demand growth for a decade, more than half of it tied to oil and gas activity. The coalition cites a study by the grid operator itself, finding that serving forecast 2038 demand would take roughly 1,676 additional miles of new line at 345 kilovolt, against about 1,255 miles at 500 kilovolt, meaning the higher voltage option needs about 25% fewer miles, a comparison this site calculated from those 2 figures. That is the case for fewer, bigger lines like the ones approved here.

New line the grid operator says 2038 Permian Basin demand needs, by voltage
05001000150020001,676345 kilovoltalternative1,255500 kilovoltalternativemiles

These 2 figures describe alternatives the grid operator studied and rejected in favor of higher voltage lines including the 765 kilovolt lines approved in this story, not a mileage figure for the approved project itself. The about 25% fewer miles comparison is a division this site made of the 2 numbers.

Source 4.

Show the numbers
345 kilovolt alternative1,676
500 kilovolt alternative1,255

Lawmakers and industry disagree on what the lines fix

Not everyone agrees it solves the real problem. Betsy Madru, a lobbyist representing the oil and gas producer Diamondback Energy, said the Permian Basin should not be treated differently from any other part of Texas.

We wouldn't expect Dallas or Houston or businesses right here in Austin to generate their own power, and the Permian Basin is no different.

Betsy Madru, lobbyist representing Diamondback Energy, an oil and gas producer. Source 1.

State Senator Kevin Sparks was blunter, and estimated the wider 765 kilovolt program could reach about 100 billion dollars over its lifetime once financing, equity returns, maintenance and taxes are counted, urging a pause for a full statewide review.

These lines do not address the primary issue of power generation.

Kevin Sparks, Texas Senate District 31. Source 2.

At an August 19 legislative hearing, State Representative Drew Darby explained that the fast clock was meant only for the Permian Basin plan, not every transmission line in the state.

When the transmission plan was brought to me, the 180 days was suggested, and it was suggested based on the Permian Basin Reliability Plan.

Drew Darby, state representative, R San Angelo. Source 3.

2 further import paths, Bell County to Ward County and Bexar County to Pecos County, remain in separate proceedings, and judges at the State Office of Administrative Hearings have already recommended denying the Bell County to Ward County route, citing cheaper alternatives.

Sources

  1. Texas approves first 765 kV lines as Permian power demand strains grid. Yahoo News, citing Texas Tribune reporting. Published 2026-08-31. Accessed 2026-09-21.
  2. Sparks responds to PUC approval of Import Path 1 and urges legislative review before further 765 kV decisions. Odessa American, via Yahoo News. Published 2026-09-03. Accessed 2026-09-21.
  3. Residents and industry leaders at odds over transmission lines at legislative hearing. Click2Houston, KPRC 2. Published 2026-08-20. Accessed 2026-09-21.
  4. TRII, what TPPF gets wrong on 765 kV, time and again. The National Law Review, press release credited to Texans for Responsible Infrastructure Investment. Published 2026-05-28. Accessed 2026-09-21.
  5. House Bill 5066, 88th Texas Legislature. Texas Legislature Online, capitol.texas.gov. Published 2023-06-13. Accessed 2026-09-21.