The biggest battery storage project in a regional grid spanning 8 states is being built in Kansas

A 424.5 megawatt battery near Garner, Kansas is the largest project in the interconnection queue for the Southwest Power Pool, the grid operator that runs the middle of the country. Oklahoma holds more total capacity signed to that grid, and Texas alone plans more new battery storage in 2026 than the whole grid queue combined.

424.5 megawatts1size of the largest battery storage project in the Southwest Power Pool queue, planned for Garner, Kansas
2,300 megawatts2battery storage capacity under signed contract in Oklahoma, the most of any state in the Southwest Power Pool grid
12.9 gigawatts5new battery storage capacity Texas plans to add nationwide in 2026

The single largest project in the queue

Southwest Power Pool is the grid operator that manages electricity flow across Kansas, Oklahoma, Nebraska, North Dakota, the Texas Panhandle and several more states. Before a new power source can connect to a grid, the operator studies it first in what is called an interconnection queue, a waiting list of projects asking permission to plug in. The single largest battery storage project anywhere in that queue, a facility that draws electricity from the grid, stores it, and sends it back later, is planned for Garner, Kansas. A study by Southwest Power Pool, finished May 22, 2025, lists the project at 424.5 megawatts, a unit of electric power, built from 93 inverters, devices that convert power between the battery and the grid, model Sungrow SC5000. It targets a connection date of June 1, 2028, at an existing substation, a facility that links power lines together, called Atlantic, rated at 345 kilovolts, a measure of electrical voltage, through transmission lines owned by Evergy Kansas Central. Adding the 2 network upgrade costs the study lists separately comes to 5,275,501 dollars.

Where Kansas actually ranks

Garner may be the single biggest project, but Kansas does not hold the most capacity signed to connect across the grid. Oklahoma leads with 2,300 megawatts under signed contract, according to Modo Energy, a firm that analyzes public interconnection data. Kansas is second at 1,100 megawatts. The Texas Panhandle, the only part of Texas inside this grid, carries just 600 megawatts.

Late stage battery storage capacity by state in the Southwest Power Pool, signed contracts as of November 2025
Oklahoma2,300Kansas1,100Texas Panhandle600Nebraska400North Dakota240New Mexico100Arkansas70Missouri5005001000150020002500megawatts

Modo Energy labels this row Texas. It is renamed Texas Panhandle here because only that part of the state sits inside the Southwest Power Pool grid, not Texas as a whole.

Source 2.

Show the numbers
Oklahoma2,300
Kansas1,100
Texas Panhandle600
Nebraska400
North Dakota240
New Mexico100
Arkansas70
Missouri50

The whole grid is filling fast

Only 300 megawatts of battery storage was operating across the grid in November 2025. By the 2026 second quarter, 8 more projects had reached operation, bringing the total to 1.4 gigawatts, a unit equal to 1,000 megawatts, across 15 projects, according to a later Modo Energy update. The firm projects 10.7 gigawatts online by 2030, 20% of everything currently signed or waiting in the queue, and more than 21 gigawatts by 2031.

Southwest Power Pool battery storage, operating capacity to projected 2030 total
0369120.3OperatingNovember 20254.8Signedlate stage10.7Projectedby 2030gigawatts

All 3 figures come from the same November 2025 report, before the 1.4 gigawatt operating total a later update reports for the 2026 second quarter.

Source 2.

Show the numbers
Operating November 20250.3
Signed late stage4.8
Projected by 203010.7

Why coverage looks like Texas

None of this compares to the scale of Texas as a whole. The Energy Information Administration, the federal agency that tracks energy data, counted 43.6 gigawatts of battery storage operating nationwide at the end of 2025, climbing to nearly 52 gigawatts by the middle of 2026, a growth rate that averaged 70% a year over the last 3 years. Texas alone is set to add 12.9 gigawatts of new battery storage in 2026, more than half of everything the country plans to add that year, according to GCN, citing federal data. This article compares those 2 figures directly. Texas growth in a single year, 12.9 gigawatts, is more than 2.6 times the entire signed and waiting queue for the whole Southwest Power Pool grid, 4.8 gigawatts.

United States battery storage capacity planned for 2026, top 3 states
05101512.9Texas3.4California3.2Arizonagigawatts planned

Based on a 24 gigawatt national planned total for 2026 that GCN states, converted from the percentage share GCN gives for each state.

Source 5.

Show the numbers
Texas12.9
California3.4
Arizona3.2

Same state, two different grids

The 600 megawatts counted for Texas inside the Southwest Power Pool grid and the 12.9 gigawatts Texas plans nationwide are not measuring the same land. Most of Texas runs on ERCOT, a separate grid outside the one this article otherwise describes. Only a sliver of Texas, mostly the Panhandle, sits inside Southwest Power Pool. The state that dominates national battery storage coverage barely registers on the one regional grid map that actually contains a piece of it. The state that holds the single largest project on that grid is Kansas.

Sources

  1. Interconnection Facilities Study Report, GEN-2020-057. Southwest Power Pool, Inc., Generator Interconnections Dept.. Published 2025-05-22. Accessed 2026-09-03.
  2. SPP battery storage buildout, the landscape. Modo Energy. Published 2025-11-12. Accessed 2026-09-03.
  3. SPP BESS buildout 2026 Q2, queue transition streamlines fleet to 1.4 gigawatts. Modo Energy. Published 2026-07-17. Accessed 2026-09-03.
  4. Battery storage capacity averaged 70% growth over the last three years. United States Energy Information Administration, Today in Energy. Published 2026-08-07. Accessed 2026-09-03.
  5. Texas to host 53 percent of all U.S. utility scale battery storage planned for 2026, EIA data show. GCN. Published 2026-08-04. Accessed 2026-09-03.