The Houston battery storage plant built in six weeks joins a Texas grid setting demand records

SMT Energy and FlexGen commissioned the 160 megawatt, 320 megawatt hour Houston IV battery in 6 weeks, a job the companies say normally takes more than 25 weeks, and connected it to the Electric Reliability Council of Texas grid the same summer that grid logged 6 straight weeks of demand above its old weekly record.

6 weeks4time SMT Energy and FlexGen took to commission the Houston IV battery storage plant, versus more than 25 weeks first estimated
135,000,000 dollars3financing SMT Energy secured for Houston IV, arranged by Macquarie and KeyBanc Capital Markets
91.1 gigawatts1new ERCOT hourly peak load record, set 22 July 2026, 6% above the 2023 record

A battery storage plant built in six weeks

SMT Energy and FlexGen built a Houston battery storage plant in six weeks, a facility that draws power from the grid, stores it in rechargeable batteries, and sends it back later, cutting the estimated build time from more than 25 weeks to 6. The plant, called Houston IV, has a nameplate capacity of 160 megawatts, how much electric power it can deliver at once, and can hold 320 megawatt hours, how much energy it can store, enough to run at full output for 2 hours before it runs empty. Irby Construction Company built the plant. Jason Rislov, senior vice president of operations at FlexGen, described the pace in an account FlexGen published itself.

What used to take 25-plus weeks took us six.

Jason Rislov, senior vice president of operations at FlexGen. Source 4.

Shaun Coleman, project manager at Irby Construction, credited the result to the same discipline.

Bringing a 160-MW battery storage facility online in just six weeks required disciplined planning, seamless coordination, and an unwavering focus on safety and quality.

Shaun Coleman, project manager at Irby Construction. Source 4.

At least the 13th project, not the 12th

Houston IV is not the 12th project the two companies have built for the Electric Reliability Council of Texas grid, known as ERCOT, the operator that runs the power grid for most of the state. The account FlexGen published about this project states Houston IV joins over a dozen prior projects built and commissioned by SMT Energy and FlexGen that actively support the ERCOT grid, totaling more than 300 megawatts of battery storage capacity. Counting Houston IV itself, that puts the total at least at 13 projects, since a group already numbering more than 12 gains one more member the moment this one joins it.

What it cost to build

SMT Energy secured 135,000,000 dollars in financing for Houston IV, arranged by Macquarie and KeyBanc Capital Markets, the banks that organized the deal, according to a press release the company issued directly. Reading that release directly also shows the scale behind the single project. SMT Energy now has 18 utility scale battery storage assets, systems built to serve the whole electric grid rather than a single home, holding about 500 megawatt hours combined, in operation or under construction. The company also states a 2 gigawatt hour pipeline, a gigawatt equal to 1,000 megawatts, of ERCOT and Southwest Power Pool battery storage projects targeted for commercial operation by 2030.

A grid setting demand records

Houston IV connected to a grid already straining under new records. ERCOT set a new hourly peak load record of 91.1 gigawatts on 22 July 2026, 6% above the prior record of 85.5 gigawatts set in August 2023. Natural gas supplied 48% of generation at that peak and solar supplied 32%, with other sources making up the rest.

Generation meeting the ERCOT peak of 91.1 gigawatts, 22 July 2026
Natural gas48Solar32Other sources2001020304050percent of generation

The 20% for other sources is this article subtracting the 48% natural gas share and the 32% solar share source 1 states from 100%. Source 1 does not name what makes up the remainder.

Source 1.

Show the numbers
Natural gas48
Solar32
Other sources20

The United States Energy Information Administration, the federal agency that tracks energy data for the country, recorded 6 straight weeks, from late July through late August 2026, when ERCOT weekly average demand exceeded its old 2023 weekly record. Average demand reached a record 74.5 gigawatts for the week ending 22 August 2026, 10% above the highest weekly average of the previous summer, before easing to 73.7 gigawatts the following week.

ERCOT weekly average electricity demand, gigawattsPrior weekly record2026 weekly average
02040608070Prior record,set 202374.5Week ending22 August 202673.7Week ending29 August 2026gigawatts

Figures are weekly average load in gigawatts, not a single hour peak. The Energy Information Administration states the prior weekly record as 70.0 gigawatts, set in 2023.

Source 5.

Show the numbers
Prior record, set 202370
Week ending 22 August 202674.5
Week ending 29 August 202673.7

Sources

  1. SMT Energy, FlexGen commission 320MWh Texas BESS in just six weeks, as ERCOT grid faces record demand. April Bonner, Energy Storage News. Published 2026-09-10. Accessed 2026-09-15.
  2. New 160MW battery storage project comes online in Houston. Mike Damante, Energy Capital HTX. Published 2026-09-14. Accessed 2026-09-15.
  3. SMT Energy Secures US135 Million For 320 MWH Battery In Houston. SMT Energy, distributed via PR Newswire. Published 2025-02-26. Accessed 2026-09-15.
  4. SMT Energy and FlexGen Deliver Battery Storage Project in Six Weeks in ERCOT. FlexGen. Published 2026-09-09. Accessed 2026-09-15.
  5. Weekly average load in ERCOT continues near record high. United States Energy Information Administration, Today in Energy. Published 2026-09-03. Accessed 2026-09-15.

Was this article helpful

Back to the home page