UK offshore wind funding for companies splits 1,000,000 pounds among 7 firms

The Offshore Wind Growth Partnership named the 7 winners on 8 September 2026, with individual awards ranging from 25,000 to 200,000 pounds toward next generation offshore wind technology.

1,000,0001pounds split among 7 UK companies in this OWGP funding round
200,0002pounds, the largest individual project award allowed in this round
25,000,0003pounds, the maximum single award allowed under the separate, larger Industrial Growth Fund

UK offshore wind funding for companies backs 7 projects

UK offshore wind funding for companies reached a new round on 8 September 2026, when the Offshore Wind Growth Partnership, known as OWGP, a UK industry group that funds new offshore wind equipment before it reaches the market, said it had split 1,000,000 pounds among 7 UK companies. Individual project awards in this round ranged from 25,000 to 200,000 pounds, open to UK based suppliers already working in offshore wind or companies trying to move into the sector. OWGP opened this call in January 2026, covering the same 2 technology areas as the winning projects, industrial foundations and substructures, and substations and electrical design. Divided evenly, the 1,000,000 pounds works out to about 142,857 pounds per company, a calculation this article makes by dividing the total by the company count, since OWGP does not report a per company figure.

What the 7 winning projects are

Acuity Robotics is building a robot, named Squirrel, that inspects the underwater legs holding a turbine steady without sending down a diver. Akselos is refining a design method, Akselos DfMA, that plans how offshore wind support structures get built and assembled in UK factories. Crondall Energy is developing a mooring system called SafeMoor, the chains and anchors that keep a floating turbine from drifting away. Fathom is upgrading METHOD, a digital model of a wind farm that updates itself as real data comes in from the farm it copies. Quoceant is building Q Connect, an underwater electrical cable link rated at 66 kilovolts, a higher voltage that lets it carry more power to shore. Sperra Seaworks is testing a concrete anchor that holds a floating turbine to the seabed by suction instead of being driven in. T12 Engineering is pairing a floating mooring system with the tools needed to install and maintain it at sea.

Why 2 energy developers are backing the fund

Equinor and SSE, 2 energy developers, back OWGP as industry champions, meaning they help choose winners. Tom Speedie, project manager at OWGP, said,

These awards reflect OWGP's commitment to backing the technologies and businesses that can strengthen the UK's offshore wind supply chain for the long term.

Tom Speedie, Project Manager at the Offshore Wind Growth Partnership. Source 1.

James Lightfoot, senior innovation manager at SSE, said,

For developers, proven technology reduces risk and increases confidence in project delivery.

James Lightfoot, Senior Innovation Manager, SSE. Source 1.

How this round compares with other OWGP funding

This round follows 2 recent ones. In February 2026, OWGP gave 5 companies a total of 1,200,000 pounds to scale up manufacturing, with each project expected to bring at least 5,000,000 pounds of investment within 2 years and at least 20 new jobs within 5 years. In December 2025, OWGP gave 9 companies a total of 2,400,000 pounds. Since OWGP started in 2019, it says it has backed more than 387 projects like these.

Total pounds awarded in the last 3 OWGP funding roundsEarlier funding roundThis funding round, September 2026
050010001500200025002400December 2025,9 companies1200February 2026,5 companies1000September 2026,7 companiesthousands of pounds

The September 2026 total is source 1. The February 2026 total is source 4. The December 2025 total is source 5. All 3 are separate OWGP funding rounds, not the same pool of money counted twice.

Source 1.

Show the numbers
December 2025, 9 companies2400
February 2026, 5 companies1200
September 2026, 7 companies1000

OWGP also runs a separate and far bigger funding tier, the Industrial Growth Fund, launched 27 October 2025, that gives 300,000 to 25,000,000 pounds to a single project. The maximum single award in that fund, 25,000,000 pounds, is 25 times the size of the entire 1,000,000 pound round this article covers, a comparison this article calculates by dividing the 2 sourced figures. OWGP says its target for 2035 is 10,000 new supply chain jobs, tripled UK manufacturing capacity, and a 25,000,000,000 pound boost to the economy.

This round against a much larger OWGP funding tier
This round, 7 companies total1000000Largest single award in the separate Industrial Growth Fund250000000500000010000000150000002000000025000000pounds

The first bar is this entire round, source 1. The second bar is the separate Industrial Growth Fund maximum single project award, source 3. Dividing 25,000,000 by 1,000,000 shows the larger fund ceiling is 25 times the size of this entire round, a comparison this article calculates, not a figure either source states directly.

Source 1.

Show the numbers
This round, 7 companies total1000000
Largest single award in the separate Industrial Growth Fund25000000

Sources

  1. Seven UK companies awarded a share of 1m to accelerate next generation offshore wind technologies. Offshore Wind Growth Partnership. Published 2026-09-08. Accessed 2026-09-29.
  2. 1m funding opportunity to back innovative offshore wind technologies. Offshore Wind Growth Partnership. Published 2026-01-27. Accessed 2026-09-29.
  3. OWGP launch Industrial Growth Fund. Offshore Wind Growth Partnership. Published 2025-10-27. Accessed 2026-09-29.
  4. Five UK companies secure 1.2m to scale offshore wind manufacturing. Offshore Wind Growth Partnership. Published 2026-02-04. Accessed 2026-09-29.
  5. OWGP awards 2.4 million to scale up UK supply chain. Offshore Wind Growth Partnership. Published 2025-12-01. Accessed 2026-09-29.

Was this article helpful

Back to the home page