Geothermal energy gets cheaper to drill as Fervo Energy signs a 320 megawatt Utah power deal

Southern California Edison signed 320 megawatts of new power purchase agreements with Fervo Energy in June 2024, a deal Utility Dive called record setting for geothermal power. A separate Fervo well drilled in 2025 cut drilling time 79% against a federal baseline, and the cost of drilling a Cape Station well fell from 9.4 million dollars to 4.8 million dollars, 2 different measurements behind the same drilling progress.

320 megawatts1of new power purchase agreements Fervo Energy signed with Southern California Edison in June 2024, under 2 15 year contracts
79%2reduction in drilling time on the Sugarloaf well, against the federal baseline for ultradeep geothermal wells
4.8 million dollars3the cost of the fourth horizontal well Fervo drilled at Cape Station, down from 9.4 million dollars for the first

Geothermal energy gets cheaper to drill

Geothermal energy, power made from heat trapped in rock deep underground, is getting cheaper and faster to drill, and a major utility is betting on it. In June 2024, Southern California Edison signed 320 megawatts, a unit of electric power, of new power purchase agreements, contracts that lock in a price and years of supply, with Fervo Energy, a company that drills geothermal wells using techniques borrowed from oil and gas fracking. Utility Dive independently confirmed the terms and called the Fervo Energy Utah geothermal power deal a record setting geothermal contract. The 2 contracts run 15 years each, bringing the total capacity under contract from Cape Station, the geothermal project Fervo Energy operates in southwest Utah, to 373 megawatts, on top of an earlier 53 megawatt deal signed with California community choice aggregators in 2022. The first phase, 70 megawatts, is due online in 2026, the rest in 2028. The deal counts toward a 2021 California mandate requiring 1,000 megawatts of power that does not depend on sun or wind.

United States geothermal capacity in context
0100020003000400050003,700United Statestotal, 2022373Cape Stationcontracted5,000Cape Stationestimated potentialmegawatts

The 3,700 figure is the total United States geothermal capacity at the time of the 2022 federal target announcement, source 4. The 5,000 figure is an independent reserves estimate for development potential at Cape Station, source 2. The 3 figures measure 3 different things, a national installed base, 1 company signed contracts at 1 site, and 1 estimate of that same site potential, not 3 points on 1 consistent scale.

Source 1.

Show the numbers
United States total, 20223,700
Cape Station contracted373
Cape Station estimated potential5,000

Enhanced geothermal systems complement our abundant wind and solar resources by providing critical base load when those sources are limited.

David Hochschild, chair of the California Energy Commission. Source 1.

The record well that cut drilling time 79%

The confidence behind that contract traces to real drilling gains, but the strongest number belongs to 1 well, not the whole project. In June 2025, Fervo drilled a well named Sugarloaf to a true vertical depth of 15,765 feet, about 4,805 meters by a MAOWCE conversion since Fervo states the figure only in feet, projected to reach 520 degrees Fahrenheit, about 271 degrees Celsius, once fully heated. Fervo finished the well in 16 drilling days, a 79% reduction in drilling time against a baseline the United States Department of Energy set for ultradeep geothermal wells. Sugarloaf is an appraisal well, drilled to test the resource, not one of the regular production wells at Cape Station, which run shallower and are not stated to reach that temperature.

A separate number for cost, not time

A second improvement covers cost rather than time, from a different set of wells. Fervo states the cost of drilling the first 4 horizontal wells at Cape Station fell from 9.4 million dollars for the first well to 4.8 million dollars for the fourth, a drop of about 49%, a MAOWCE calculation from those 2 stated dollar figures since Fervo never states the percentage itself. Fervo also states a 70% year over year reduction in drilling time across its wider well program, a third and separate measurement from the Sugarloaf figure above. None of these 3 percentages describe the same comparison, and none should be added together into 1 number.

Cost to drill a Cape Station well, first well against the fourth
02468109.4Firsthorizontal well4.8Fourthhorizontal wellmillion dollars a well

Figures are for the first 4 horizontal wells drilled at Cape Station, source 3. The drop from the first well to the fourth is about 49%, a MAOWCE calculation from the 2 dollar figures the source states, not a percentage source 3 itself gives.

Source 3.

Show the numbers
First horizontal well9.4
Fourth horizontal well4.8

Fervo's drilling improvements are like the early days of the shale revolution.

Trey Lowe, chief technology officer of Devon Energy, an oil and gas company with its own commercial interest in enhanced geothermal drilling technique adoption. Source 3.

The federal target this drilling progress is racing against

The United States Department of Energy set a goal in 2022 to cut geothermal power costs 90% to 45 dollars per megawatt hour by 2035, aiming at more than 5 terawatts, a unit equal to 1,000 gigawatts, of heat the agency says sits under the country, enough potential to power over 40 million homes. United States geothermal capacity stood at about 3.7 gigawatts, a unit equal to 1,000 megawatts, at the time. Fervo signing a 320 megawatt contract, and cutting drilling time and cost the way its own releases describe, both happened years before that 2035 target date.

Sources

  1. Fervo Energy Announces 320 MW Power Purchase Agreements with Southern California Edison. Fervo Energy. Published 2024-06-25. Accessed 2026-09-14.
  2. Fervo Energy Drills 15,000 FT, 500 F Geothermal Well Pushing The Envelope For EGS Deployment. Fervo Energy. Published 2025-06-10. Accessed 2026-09-14.
  3. Fervo Energy Drilling Results Show Rapid Advancement of Geothermal Performance. Fervo Energy. Published 2024-02-12. Accessed 2026-09-14.
  4. DOE Launches New Energy Earthshot to Slash the Cost of Geothermal Power. United States Department of Energy. Published 2022-09-08. Accessed 2026-09-14.
  5. Fervo, Southern California Edison ink record setting 320 MW geothermal deal. Utility Dive, byline Diana DiGangi. Published 2024-06-28. Accessed 2026-09-14.

Was this article helpful

Back to the home page